Project Name:
CHINA ENERGY INVESTMENT HAIJING SALT FIELD 500KV PHOTOVOLTAIC STEP-UP SUBSTATION
-
Project Time:
2024
Project Introduction:
Pain Point 1: Equipment corrosion in high-salt fog environments
Adopted TGOOD's fully pre-fabricated modular substation with C5-M anti-corrosion treatment, ensuring lifecycle protection for equipment.
Pain Point 2: Tight construction schedule
Achieved over 90% factory pre-fabrication rate, reducing on-site installation to 40 days, enabling 580MW full-capacity grid connection within 1 year.
Pain Point 3: High costs
Pioneered 500kV pre-fabricated substation and temporary grid-connection solutions, shortening schedule by 30% and reducing overall costs by 150 million yuan through modular construction.