Project Name:

CHINA SOUTHERN POWER GRID SHENZHEN POWER RENOVATION DISTRIBUTION SUBSTATION PROJECT

Project Time:

2023

Project Introduction:

One city, one strategy, creating a versatile and adaptable electric Rubik's Cube, achieving environmental friendliness and reducing the "neighborhood avoidance effect".

Factory prefabrication, all internal primary and secondary equipment are prefabricated and assembled in the factory, and delivered as a complete set for the entire station.

Mechanical construction, on-site building block assembly, realizing the transformation from construction to purchase, completion upon delivery, reducing the impact of construction on surrounding residents.

Layout optimization, achieving a 30% -50% reduction in land area, better fitting the urban village scene, and facilitating site selection.

Construction period: The overall delivery time is 35 days, and the on-site civil construction period has been compressed from 45 days to 5 days